A re-roof is one of the most common reasons we get called out - and one of the most common ways the asbestos step gets bolted on as an afterthought rather than planned properly from the start.
Why order matters here
Roofing contractors aren't licensed to remove asbestos, and for good reason - it's a different trade with different training and equipment. If your existing roof contains asbestos, it has to come off first, by a licensed removalist, before your roofer can install anything new.
The sequence that actually works
- Get the existing roof assessed - confirm whether it's asbestos before anything else is booked
- Book asbestos removal - scheduled and quoted as its own phase
- Clearance certificate issued - the site is confirmed safe before any new trade starts
- New roof installation begins - your roofer works on a clean, cleared structure
Why skipping ahead causes problems
We've seen roofing jobs get held up - sometimes for weeks - because a roofer arrived to find asbestos sheeting that hadn't been flagged or removed. Beyond the delay, having a roofing crew work around (or worse, over) asbestos sheeting without proper removal is a genuine safety and compliance issue for everyone on site.
We can coordinate directly with your roofer
If you've already got a roofing contractor lined up, we're happy to liaise directly with them on timing, so the removal and the new roof installation run back to back rather than leaving your property exposed to the weather for longer than necessary.
One quote, one timeline
We can quote the asbestos removal and, if useful, coordinate the new roof install as part of the same conversation - so you're managing one project, not juggling two contractors with no idea what the other is doing.
Get a quote for your re-roof - we'll help you plan the whole sequence, not just our part of it.